Tanathi WWDA had received funds from the Gok towards implementation of Kiambere-Mwingi Phase II lase Mile connectivity project to supply water to Kakunike, Kathumbini, Kwa Nguru and Tulanduli market centres. The principle objective was to improve water availability and health issue among the areas. The project is at Kyuso ward in Mwingi North Constituency at Kitui County
The scope of works contracted was to get water from Kiambere-Mwingi main line GPS (N 9921135.66, E 398815.11 Z 996.25m, 1No. Booster station, Raising main, Water tanks (3No. 225m3 Ground Masonry Tanks, 10M3 Elevated plastic tank, and 100m3 Elevated steel tank), Distribution line, Water kiosks STD valve chambers and marker post, thrust and anchor blocks. Start date of the contract was 6/2/2020 and completion date was expected to be 26/03/2021. Contracted amount was Kshs 58.334.892. During the time of visit, project completion rate was 75%.