Tanathi WWDA had received funds from the Gok towards implementation of Kiambere-Mwingi Phase II last Mile connectivity project to supply water to Kakunike, Kathumbini, Kwa Nguru and Tulanduli market centres. The principle objective was to improve water availability and health within the target areas. The project is within Kyuso ward in Mwingi North Constituency, Kitui County.
The scope of works contracted was to get water from Kiambere-Mwingi main line GPS (N 9921135.66, E 398815.11 Z 996.25m, 1No. Booster station, Raising main, Water tanks (3No. 225m3 Ground Masonry Tanks, 10M3 and 100m3 Elevated steel tank), Distribution line, 4No.Water kiosks STD valve chambers and marker post, thrust and anchor blocks all with a cost of Ksh. 58,334,892. besiktas escort Start date of the contract was 6/2/2020 and completion date was expected to be 26/03/2021. The contractor had requested for three month extension period which was yet granted by the time of visit. Overall projects completion rate at that time was 97%.
Pictorial Evidence
FIELD PHOTO |
DESCRIPTION |
First masonry water tank and booster pump constructed on a community group land at Kwa Ngundu village. The site is well fenced with mesh wire and agate was fabricated and installed. |
|
At the booster tank there is booster pump inside a masonry constructed half way and finished with timber woods and wire mesh. |
|
Control panels inside the pump house | |
Elevated steel stand for the steel tank which is 95% complete and water kiosk which was complete by the time of visit Kakunike village. |
|
Second masonry water tank and the water kiosk which were all completed by the time of visit at Kathumbini village. |
|
Third masonry water tank and the water kiosk ongoing by the time of visit at Kwa Nguru village. GPS-CORDINATES Latitude: -0.692552 Longitude:38.137820 Altitude:1068.6 |
|
Intake in main line of Kiambere mwingi phase one connected. |